by Daniel Gray | Mar 6, 2024 | Project Progress
Project Progress As previously mentioned this project is in the completion phase. At present, all buildings are complete. We now await the electrics and water to be connected before we can commission and test. The external ground works are ongoing and prepping for...
by Daniel Gray | Feb 28, 2024 | Project Progress
Project Progress Despite some adverse weather implications, we have now completed the additional roofing works that were required and have commenced the striking of the scaffold, which continues to be on target. Internal works to make good reveals are progressing...
by Daniel Gray | Dec 13, 2023 | Community Work
On the evening of the 4th & 11th of December, we had the pleasure to go out with Santa in tow and carry out some of the annual door to door collections for Keech Hospice Care in the Riverfield Drive & Markham Rise areas of Bedford. Both nights were very well...
by Daniel Gray | Dec 1, 2023 | Project Progress
Luton Town Hall external refurbishment is well under way, pictured are just a few of the windows replaced on the fourth floor along with the lead works to the roof. The project is progressing very well and will be completed on time and within budget, despite weather...
by Daniel Gray | Nov 28, 2023 | Project Progress
The Chalklands PH3 project is progressing very well and is fast approaching the completion phase of the project. The internal works are nearing finishing point and the external works are now in progress. We are working towards a March 2024 completion. #grayandsons...